Dept. of Trans. SEMI-FINAL Serial No. Contract No. 20-315-08-35 10-0X7104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-SJ-99-5.4/6.2 ACNH-X077(27) 10-SJ-120-R2.6/T7.2 Progress payment No. 011 Payment period ending: 06-26-20 PACIFIC INFRASTRUCTURE CONSTRUCTION LLC 871 COTTING CT #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,135,385.38 0.00 2. a. Extra Work 128,436.17 12,393.51 b. Adustment Comp. -8,638.61 23,861.20 3. Materials on Hand 4. Earned Subject to Retention 2,255,182.94 36,254.71 5. Mobilization 277,000.00 0.00 6. Total Work Completed 2,532,182.94 7. Deductions -1,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,531,182.94 46,254.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 46,254.71