Dept. of Trans. PROGRESS Serial No. Contract No. 24-055-12-25 10-0X7524 PROGRESS PAYMENT VOUCHER %complete: %time: 14% 24% Location: Federal Project: 10-AMA-49-0.0 NONE 10-CAL-49-30.9 Progress payment No. 004 Payment period ending: 02-20-24 BRIDGEWAY CIVIL CONSTRUCTORS INC 3333 VACA VALLEY PKWY #2000 B VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 340,334.00 66,482.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 340,334.00 66,482.00 5. Mobilization 185,000.00 0.00 6. Total Work Completed 525,334.00 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 515,334.00 56,482.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 56,482.00