Dept. of Trans. PROGRESS Serial No. Contract No. 14-265-08-27 10-0X7804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 75% 10-SJ-5-R19.6/R23.9 Federal Project: 10-SJ-26-1.9/ .0 NONE 10-SJ-88-0.0/ .0 Progress payment No. 02 Payment period ending: 09-20-14 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION, INC. 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 95,886.84 30,473.36 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 95,886.84 30,473.36 5. Mobilization 42,000.00 14,000.00 6. Total Work Completed 137,886.84 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -3,047.34 -3,047.34 c. Reduction after 95% Comp. 9. Total pay to Contractor 134,839.50 41,426.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 41,426.02