Dept. of Trans. PROGRESS Serial No. Contract No. 21-144-16-33 10-0Y1104 PROGRESS PAYMENT VOUCHER %complete: %time: 45% 30% Location: Federal Project: 10-MER-140-0.0/42.1 HSNH-P140(38) Progress payment No. 003 Payment period ending: 05-20-21 MIDSTATE BARRIER INC PO BOX 30550 STOCKTON CA 95213-0550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,171,762.70 461,986.80 2. a. Extra Work 9,610.00 9,610.00 b. Adustment Comp. 2,250.00 2,250.00 3. Materials on Hand 99,490.16 -22,269.20 4. Earned Subject to Retention 1,283,112.86 451,577.60 5. Mobilization 152,000.00 0.00 6. Total Work Completed 1,335,622.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,435,112.86 451,577.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 451,577.60