Dept. of Trans. SEMI-FINAL Serial No. Contract No. 14-339-08-25 10-0Y1204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-MER-59-7.9/14.1 Federal Project: NONE Progress payment No. 04 Payment period ending: 11-03-14 A. TEICHERT & SON, INC DBA TEICHERT CONSTRUCTION P O BOX 520 FOWLER, CA 93625-0520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,809,435.20 4,212.45 2.a. Extra Work 12,443.18 6,537.85 b. Adjustment Comp. -39,491.27 -39,491.27 3. Materials on Hand 4. Earned Subject to Retention 1,782,387.11 -28,740.97 5. Mobilization 6. Total Work Completed 1,782,387.11 7. Deductions -5,000.00 60,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,777,387.11 31,259.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 31,259.03