Dept. of Trans. PROGRESS Serial No. Contract No. 24-023-14-23 10-0Y1304 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 81% Location: Federal Project: 10-MER-140-2.3/49.0 HSNH-P140(42) Progress payment No. 005 Payment period ending: 01-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,230,775.86 511,789.91 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -98,787.87 4. Earned Subject to Retention 2,230,775.86 413,002.04 5. Mobilization 270,000.00 0.00 6. Total Work Completed 2,500,775.86 7. Deductions -10,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,490,775.86 423,002.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 423,002.04