Dept. of Trans. PROGRESS Serial No. Contract No. 23-297-12-41 10-0Y7804 PROGRESS PAYMENT VOUCHER %complete: %time: 57% 11% Location: Federal Project: 10-MPA-140-25.3/51.8 ACNH-P140(40) Progress payment No. 003 Payment period ending: 10-20-23 TEICHERT CONSTRUCTION 3500 AMERICAN RIVER DRIVE SACRAMENTO CA 95864 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,054,611.50 4,594,018.55 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 12,054,611.50 4,594,018.55 5. Mobilization 2,211,771.00 0.00 6. Total Work Completed 14,266,382.50 7. Deductions -4,000.00 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,262,382.50 4,590,018.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,590,018.55