Dept. of Trans. PROGRESS Serial No. Contract No. 16-081-08-23 10-1C0004 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 34% Location: Federal Project: 10-SJ-4-0.0 STP-000C(395) 10-SJ-5-0.0 10-SJ-99-0.0 Progress payment No. 003 Payment period ending: 03-20-16 HIGHWAY SPECIALTY COMPANY INC PO BOX 141 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 609,326.48 269,135.28 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 609,326.48 269,135.28 5. Mobilization 25,000.00 1,250.00 6. Total Work Completed 634,326.48 7. Deductions -15,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 619,326.48 260,385.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 260,385.28