Dept. of Trans. PROGRESS Serial No. Contract No. 16-111-14-06 10-1C0004 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 60% Location: Federal Project: 10-SJ-4-0.0 STP-000C(395) 10-SJ-5-0.0 10-SJ-99-0.0 Progress payment No. 004 Payment period ending: 04-20-16 HIGHWAY SPECIALTY COMPANY INC PO BOX 141 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 631,371.21 22,044.73 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 631,371.21 22,044.73 5. Mobilization 25,000.00 0.00 6. Total Work Completed 656,371.21 7. Deductions -30,000.00 -15,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 626,371.21 7,044.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,044.73