Dept. of Trans. PROGRESS Serial No. Contract No. 15-055-13-08 10-1C0204 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 33% Location: Federal Project: 10-SJ-12-R4.4 NHP-P012(118) Progress payment No. 003 Payment period ending: 02-20-15 WEST COAST STRUCTURS INC DBA WESTERN STRUCTURES 6005 TYLER STREET RIVERSIDE CA 92503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 378,897.68 184,701.12 2. a. Extra Work 14,453.45 14,453.45 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 393,351.13 199,154.57 5. Mobilization 153,021.51 32,215.05 6. Total Work Completed 546,372.64 7. Deductions -38,136.40 -8,028.72 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 508,236.24 223,340.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 223,340.90