Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 15-198-09-05 10-1C0304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-TUO-108-2.0/2.0 HSNH-X019(29) Progress payment No. 003 Payment period ending: 07-09-15 CCFG CONSTRUCTION 393 MORNING STAR DR SONORA CA 95370 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 212,516.04 6,382.64 2. a. Extra Work 17,521.30 16,770.53 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 230,037.34 23,153.17 5. Mobilization 6. Total Work Completed 230,037.34 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 225,037.34 18,153.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,153.17