Dept. of Trans. PROGRESS Serial No. Contract No. 19-168-10-32 10-1C0604 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 72% Location: Federal Project: 10-SJ-99-0.9 ACNH-P099(632) 10-SJ-99-31.6 Progress payment No. 003 Payment period ending: 06-20-19 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 490,836.18 273,997.20 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 490,836.18 273,997.20 5. Mobilization 32,270.00 1,613.50 6. Total Work Completed 523,106.18 7. Deductions -27,399.72 -27,399.72 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 495,706.46 248,210.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 248,210.98