Dept. of Trans. PROGRESS Serial No. Contract No. 22-263-09-43 10-1C1704 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 33% Location: Federal Project: 10-MER-99-R12.7/17.8 ACNH-P099(662) Progress payment No. 015 Payment period ending: 09-20-22 TEICHERT CONSTRUCTION 3500 AMERICAN RIVER DRIVE SACRAMENTO CA 95864 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,669,957.83 1,394,256.90 2. a. Extra Work 692,624.77 2,296.44 b. Adustment Comp. 446,757.39 0.00 3. Materials on Hand 502,386.83 502,386.83 4. Earned Subject to Retention 15,311,726.82 1,898,940.17 5. Mobilization 4,275,000.00 0.00 6. Total Work Completed 19,084,339.99 7. Deductions -25,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 19,561,726.82 1,888,940.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,888,940.17