Dept. of Trans. PROGRESS Serial No. Contract No. 23-083-13-34 10-1C1704 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 51% Location: Federal Project: 10-MER-99-R12.7/17.8 ACNH-P099(662) Progress payment No. 021 Payment period ending: 03-20-23 TEICHERT CONSTRUCTION 3500 AMERICAN RIVER DRIVE SACRAMENTO CA 95864 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,006,583.38 84,066.16 2. a. Extra Work 1,462,370.74 5,921.19 b. Adustment Comp. 1,476,549.80 0.00 3. Materials on Hand 400,761.81 0.00 4. Earned Subject to Retention 23,346,265.73 89,987.35 5. Mobilization 4,500,000.00 0.00 6. Total Work Completed 27,445,503.92 7. Deductions -30,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 27,816,265.73 84,987.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 84,987.35