Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 24-250-13-38 10-1C1704 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 100% Location: Federal Project: 10-MER-99-R12.7/17.8 ACNH-P099(662) Progress payment No. 042 Payment period ending: 08-20-24 TEICHERT CONSTRUCTION 3500 AMERICAN RIVER DRIVE SACRAMENTO CA 95864 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,796,225.41 70,839.55 2. a. Extra Work 6,137,545.11 318,026.47 b. Adustment Comp. 3,880,421.43 0.00 3. Materials on Hand 4. Earned Subject to Retention 50,814,191.95 388,866.02 5. Mobilization 4,500,000.00 0.00 6. Total Work Completed 55,314,191.95 7. Deductions -85,000.01 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 55,229,191.94 388,866.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 388,866.02