Dept. of Trans. PROGRESS Serial No. Contract No. 16-172-10-24 10-1C2104 PROGRESS PAYMENT VOUCHER %complete: %time: 35% 44% Location: Federal Project: 10-SJ-5 NHP-000C(419) 10-SJ-205 10-ALA-580 Progress payment No. 003 Payment period ending: 06-20-16 ST FRANCIS ELECTRIC INC PO BOX 2057 SAN LEANDRO CA 94577 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 951,250.65 381,433.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 214,506.11 0.00 4. Earned Subject to Retention 1,165,756.76 381,433.00 5. Mobilization 104,500.00 0.00 6. Total Work Completed 1,055,750.65 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,270,256.76 381,433.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 381,433.00