Dept. of Trans. PROGRESS Serial No. Contract No. 25-170-14-12 10-1C2704 PROGRESS PAYMENT VOUCHER %complete: %time: 55% 70% Location: Federal Project: 10-STA-5-27.1/27.4 CIMG-005(5) Progress payment No. 012 Payment period ending: 06-20-25 TSI ENGINEERING INC 4600 ROSEVILLE RD #140 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,161,991.92 922,086.65 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 938,190.17 422,268.39 4. Earned Subject to Retention 12,100,182.09 1,344,355.04 5. Mobilization 6. Total Work Completed 11,161,991.92 7. Deductions -10,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,090,182.09 1,354,355.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,354,355.04