Dept. of Trans. PROGRESS Serial No. Contract No. 25-217-13-53 10-1C2704 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 81% Location: Federal Project: 10-STA-5-27.1/27.4 CIMG-005(5) Progress payment No. 014 Payment period ending: 08-04-25 TSI ENGINEERING INC 4600 ROSEVILLE RD #140 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,508,193.15 4,250.00 2. a. Extra Work 99,201.81 99,201.81 b. Adustment Comp. 3. Materials on Hand 468,816.00 0.00 4. Earned Subject to Retention 13,076,210.96 103,451.81 5. Mobilization 6. Total Work Completed 12,607,394.96 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 87,257.71 c. Reduction after 95% Comp. 9. Total pay to Contractor 13,056,210.96 190,709.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 190,709.52