Dept. of Trans. PROGRESS Serial No. Contract No. 22-026-07-39 10-1C2804 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 92% Location: Federal Project: 10-SJ-99-30.9/31.3 ACNH-P099(661) Progress payment No. 012 Payment period ending: 01-20-22 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,194,388.31 601,202.80 2. a. Extra Work 69,822.42 10,517.10 b. Adustment Comp. 134,579.17 -865.00 3. Materials on Hand 201,068.15 -80,740.33 4. Earned Subject to Retention 4,599,858.05 530,114.57 5. Mobilization 665,000.00 0.00 6. Total Work Completed 5,063,789.90 7. Deductions -154,552.00 -29,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,110,306.05 501,114.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 501,114.57