Dept. of Trans. PROGRESS Serial No. Contract No. 23-023-16-07 10-1C2804 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 100% Location: Federal Project: 10-SJ-99-30.9/31.3 ACNH-P099(661) Progress payment No. 024 Payment period ending: 01-20-23 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,687,802.22 8,905.00 2. a. Extra Work 201,584.96 34,283.36 b. Adustment Comp. 331,215.39 -863.85 3. Materials on Hand 4. Earned Subject to Retention 10,220,602.57 42,324.51 5. Mobilization 700,000.00 0.00 6. Total Work Completed 10,920,602.57 7. Deductions -576,259.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,344,343.57 42,324.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 42,324.51