Dept. of Trans. PROGRESS Serial No. Contract No. 20-143-13-27 10-1C3004 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 96% Location: Federal Project: 10-STA-99-R20.9/R24.7 ACNH-P099(616) 10-SJ-99-0.0/6.8 Progress payment No. 024 Payment period ending: 05-20-20 BAY CITIES PAVING& GRADING INC 1450 CIVIC CT BLDG B #400 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,157,176.39 19,579.56 2. a. Extra Work 465,902.18 136,023.15 b. Adustment Comp. 102,687.45 0.00 3. Materials on Hand 4. Earned Subject to Retention 11,725,766.02 155,602.71 5. Mobilization 500,000.00 0.00 6. Total Work Completed 12,225,766.02 7. Deductions -120,670.78 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,105,095.24 145,602.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 145,602.71