Dept. of Trans. PROGRESS Serial No. Contract No. 24-173-14-17 10-1C3804 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 42% Location: Federal Project: 10-SJ-205-L0.0/R13.2 HSIM-205(6) Progress payment No. 007 Payment period ending: 06-20-24 MIDSTATE BARRIER INC PO BOX 30550 STOCKTON CA 95213-0550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,687,820.40 260,844.40 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 312,595.92 -45,944.16 4. Earned Subject to Retention 2,000,416.32 214,900.24 5. Mobilization 228,000.00 0.00 6. Total Work Completed 1,915,820.40 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,228,416.32 214,900.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 214,900.24