Dept. of Trans. PROGRESS Serial No. Contract No. 17-114-09-32 10-1C4904 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 70% Location: Federal Project: 10-MER-33-17.4/26.4 ACHS-STPG-P(33) 10-STA-33-1.4/27.0 Progress payment No. 002 Payment period ending: 04-20-17 LINEAR OPTIONS INC 792 DURHAM DAYTON HWY DURHAM CA 95938 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 492,001.42 94,685.74 2. a. Extra Work 13,519.61 3,145.87 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 505,521.03 97,831.61 5. Mobilization 6. Total Work Completed 505,521.03 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 505,521.03 97,831.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 97,831.61