Dept. of Trans. PROGRESS Serial No. Contract No. 22-357-12-00 10-1C5004 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 96% Location: Federal Project: 10-SJ-4-R15.5/R16.7 ACNH-X077(28) Progress payment No. 019 Payment period ending: 12-20-22 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,374,270.66 156,389.00 2. a. Extra Work 717,104.55 48,726.54 b. Adustment Comp. 124,262.45 0.00 3. Materials on Hand 631,968.54 0.00 4. Earned Subject to Retention 23,847,606.20 205,115.54 5. Mobilization 1,019,279.00 0.00 6. Total Work Completed 24,234,916.66 7. Deductions -184,250.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 24,682,635.20 205,115.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 205,115.54