Dept. of Trans. PROGRESS Serial No. Contract No. 23-172-10-05 10-1C7904 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 73% Location: Federal Project: 10-MER-5-0.5/0.8 CIMG-005-5(156) Progress payment No. 015 Payment period ending: 06-20-23 WALSH CONSTRUCTION COMPANY II LLC 1390 WILLOW PASS RD #950 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,472,622.09 1,550,861.29 2. a. Extra Work 18,881.17 2,556.78 b. Adustment Comp. 40,210.80 40,210.80 3. Materials on Hand 900,957.00 -94,681.00 4. Earned Subject to Retention 19,432,671.06 1,498,947.87 5. Mobilization 6. Total Work Completed 18,531,714.06 7. Deductions -30,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 19,402,671.06 1,498,947.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,498,947.87