Dept. of Trans. PROGRESS Serial No. Contract No. 23-361-11-23 10-1C7904 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 87% Location: Federal Project: 10-MER-5-0.5/0.8 CIMG-005-5(156) Progress payment No. 021 Payment period ending: 12-20-23 WALSH CONSTRUCTION COMPANY II LLC 1390 WILLOW PASS RD #950 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,613,252.42 676,738.83 2. a. Extra Work 169,544.34 0.00 b. Adustment Comp. 372,428.83 0.00 3. Materials on Hand 100,000.00 100,000.00 4. Earned Subject to Retention 28,255,225.59 776,738.83 5. Mobilization 6. Total Work Completed 28,155,225.59 7. Deductions -120,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 28,135,225.59 766,738.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 766,738.83