Dept. of Trans. PROGRESS Serial No. Contract No. 25-150-15-30 10-1C7904 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 100% Location: Federal Project: 10-MER-5-0.5/0.8 CIMG-005-5(156) Progress payment No. 028 Payment period ending: 05-20-25 WALSH CONSTRUCTION COMPANY II LLC 1390 WILLOW PASS RD #950 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,515,002.23 -472,940.00 2. a. Extra Work 2,117,040.85 1,821,332.00 b. Adustment Comp. 772,958.61 50,670.20 3. Materials on Hand 4. Earned Subject to Retention 31,405,001.69 1,399,062.20 5. Mobilization 6. Total Work Completed 31,405,001.69 7. Deductions -90,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 31,315,001.69 1,409,062.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,409,062.20