Dept. of Trans. SEMI-FINAL Serial No. Contract No. 17-145-10-39 10-1E1004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-SJ-4-R16.0/R18.5 NONE 10-SJ-5-25.8/47.6 Progress payment No. 008 Payment period ending: 04-28-17 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 538,805.14 0.00 2. a. Extra Work 25,624.08 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 564,429.22 0.00 5. Mobilization 64,000.00 0.00 6. Total Work Completed 628,429.22 7. Deductions -10,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 618,429.22 10,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,000.00