Dept. of Trans. PROGRESS Serial No. Contract No. 16-172-10-31 10-1E1304 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 16% Location: Federal Project: 10-MER-0-0.0 NONE Progress payment No. 001 Payment period ending: 06-20-16 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 38,482.50 38,482.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 38,482.50 38,482.50 5. Mobilization 36,000.00 36,000.00 6. Total Work Completed 74,482.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 74,482.50 74,482.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 74,482.50