Dept. of Trans. SEMI-FINAL Serial No. Contract No. 16-321-14-48 10-1E1304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-MER-0-0.0 NONE Progress payment No. 006 Payment period ending: 10-10-16 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 678,902.80 0.00 2. a. Extra Work 25,160.39 25,073.43 b. Adustment Comp. -750.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 703,313.19 25,073.43 5. Mobilization 72,000.00 0.00 6. Total Work Completed 775,313.19 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 765,313.19 25,073.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 25,073.43