Dept. of Trans. PROGRESS Serial No. Contract No. 23-115-15-34 10-1E6104 PROGRESS PAYMENT VOUCHER %complete: %time: 5% 8% Location: Federal Project: 10-SJ-4 NONE 10-SJ-99 10-SJ-120-0.0 Progress payment No. 001 Payment period ending: 04-20-23 KOCH & KOCH INC 13084 JOHN BAUER AVE GRASS VALLEY CA 95945 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 211,709.12 211,709.12 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 211,709.12 211,709.12 5. Mobilization 6. Total Work Completed 211,709.12 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 211,709.12 211,709.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 211,709.12