Dept. of Trans. PROGRESS Serial No. Contract No. 24-064-18-05 10-1E6104 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 30% Location: Federal Project: 10-SJ-4 NONE 10-SJ-99 10-SJ-120-0.0 Progress payment No. 009 Payment period ending: 02-20-24 KOCH & KOCH INC 13084 JOHN BAUER AVE GRASS VALLEY CA 95945 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 798,851.00 0.00 2. a. Extra Work 8,572.27 2,581.24 b. Adustment Comp. 3. Materials on Hand 673,690.00 181,034.00 4. Earned Subject to Retention 1,481,113.27 183,615.24 5. Mobilization 6. Total Work Completed 807,423.27 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,481,113.27 183,615.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 183,615.24