Dept. of Trans. SEMI-FINAL Serial No. Contract No. 24-117-09-43 10-1E6204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-MER-99 NONE Progress payment No. 027 Payment period ending: 03-25-24 DISNEY CONSTRUCTION INC 533 AIRPORT BLVD #120 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,236,518.00 0.00 2. a. Extra Work 147,159.05 10,650.00 b. Adustment Comp. 587,952.71 33,171.24 3. Materials on Hand 4. Earned Subject to Retention 5,971,629.76 43,821.24 5. Mobilization 520,000.00 0.00 6. Total Work Completed 6,491,629.76 7. Deductions -8,033.80 15,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,483,595.96 58,821.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 58,821.24