Dept. of Trans. PROGRESS Serial No. Contract No. 16-021-14-15 10-1E9604 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 88% Location: Federal Project: 10-MER-5-0.5/0.5 NONE Progress payment No. 004 Payment period ending: 01-20-16 DIEDE CONSTRUCTION INC PO BOX 1007 WOODBRIDGE CA 95258 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 395,311.53 24,724.96 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 395,311.53 24,724.96 5. Mobilization 6. Total Work Completed 395,311.53 7. Deductions -6,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 389,311.53 22,724.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 22,724.96