Dept. of Trans. PROGRESS Serial No. Contract No. 17-325-10-40 10-1F1604 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 53% Location: Federal Project: 10-MER-33-R16.1 NONE Progress payment No. 003 Payment period ending: 11-20-17 VIKING CONSTRUCTION CO INC 11315 SUNRISE GOLD CIR #A RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 514,580.00 462,080.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 514,580.00 462,080.00 5. Mobilization 114,000.00 54,000.00 6. Total Work Completed 628,580.00 7. Deductions -51.68 -24.48 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 628,528.32 516,055.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 516,055.52