Dept. of Trans. PROGRESS Serial No. Contract No. 22-168-09-11 10-1F1704 PROGRESS PAYMENT VOUCHER %complete: %time: 30% 34% Location: Federal Project: 10-SJ-26-1.1/1.1 NONE 10-SJ-99-19.3/19.3 Progress payment No. 004 Payment period ending: 06-20-22 ANDREW M JORDAN INC DBA A & B CONSTRUCTION 1350 4TH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,190,263.40 177,790.00 2. a. Extra Work 13,640.00 1,650.00 b. Adustment Comp. 3. Materials on Hand 269,793.00 0.00 4. Earned Subject to Retention 1,473,696.40 179,440.00 5. Mobilization 541,500.00 0.00 6. Total Work Completed 1,745,403.40 7. Deductions -51,000.00 -35,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,964,196.40 144,440.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 144,440.00