Dept. of Trans. PROGRESS Serial No. Contract No. 25-022-15-29 10-1F1804 PROGRESS PAYMENT VOUCHER %complete: %time: 50% 49% Location: Federal Project: 10-SJ-4-R16.0/R19.4 ACNH-P004(162) Progress payment No. 011 Payment period ending: 01-20-25 VIKING CONSTRUCTION CO INC PO BOX 1508 RANCHO CORDOVA CA 95741-1508 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,872,267.50 720,692.00 2. a. Extra Work 208,099.32 0.00 b. Adustment Comp. 3. Materials on Hand 282,315.00 -253,144.00 4. Earned Subject to Retention 11,362,681.82 467,548.00 5. Mobilization 2,470,000.00 0.00 6. Total Work Completed 13,550,366.82 7. Deductions -232,000.00 -42,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,600,681.82 425,548.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 425,548.00