Dept. of Trans. PROGRESS Serial No. Contract No. 24-239-14-59 10-1F4004 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 89% Location: Federal Project: 10-VAR-4-0.0 NONE Progress payment No. 014 Payment period ending: 08-20-24 TENNYSON ELECTRIC LLC 7275 NATIONAL DRIVE #A2 LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,179,768.25 261,616.00 2. a. Extra Work 349,215.48 0.00 b. Adustment Comp. -103,548.30 -130,682.00 3. Materials on Hand 4. Earned Subject to Retention 8,425,435.43 130,934.00 5. Mobilization 565,000.00 0.00 6. Total Work Completed 8,990,435.43 7. Deductions -134,425.80 -114,425.80 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,856,009.63 16,508.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 16,508.20