Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 21-300-15-01 10-1F4304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-MER-140-35.9/36.9 NONE Progress payment No. 003 Payment period ending: 09-20-21 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 672,354.10 298,509.60 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 672,354.10 298,509.60 5. Mobilization 63,900.00 0.00 6. Total Work Completed 736,254.10 7. Deductions -22,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 714,254.10 278,509.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 278,509.60