Dept. of Trans. PROGRESS Serial No. Contract No. 21-113-16-26 10-1F8304 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 44% Location: Federal Project: 10-AMA-49-4.0/4.2 NONE Progress payment No. 003 Payment period ending: 04-20-21 SERAFIX ENGINEERING CONTRACTORS INC 7 CROW CANYON CT #250 SAN RAMON CA 94583 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 419,426.00 188,464.00 2. a. Extra Work 23,200.00 13,200.00 b. Adustment Comp. -2,040.00 0.00 3. Materials on Hand 8,097.98 -4,299.21 4. Earned Subject to Retention 448,683.98 197,364.79 5. Mobilization 95,000.00 0.00 6. Total Work Completed 535,586.00 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 541,683.98 197,364.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 197,364.79