Dept. of Trans. PROGRESS Serial No. Contract No. 21-145-09-24 10-1F8304 PROGRESS PAYMENT VOUCHER %complete: %time: 74% 69% Location: Federal Project: 10-AMA-49-4.0/4.2 NONE Progress payment No. 004 Payment period ending: 05-20-21 SERAFIX ENGINEERING CONTRACTORS INC 7 CROW CANYON CT #250 SAN RAMON CA 94583 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 714,158.00 294,732.00 2. a. Extra Work 23,200.00 0.00 b. Adustment Comp. -2,040.00 0.00 3. Materials on Hand 0.00 -8,097.98 4. Earned Subject to Retention 735,318.00 286,634.02 5. Mobilization 100,000.00 5,000.00 6. Total Work Completed 835,318.00 7. Deductions 0.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 835,318.00 293,634.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 293,634.02