Dept. of Trans. PROGRESS Serial No. Contract No. 18-295-12-58 10-1G5004 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 43% Location: Federal Project: 10-MER-5-25.9/32.1 NONE 10-STA-5-2.4/10.7 Progress payment No. 004 Payment period ending: 10-20-18 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,190,819.25 1,045,252.75 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -24,500.00 4. Earned Subject to Retention 1,190,819.25 1,020,752.75 5. Mobilization 226,100.00 107,100.00 6. Total Work Completed 1,416,919.25 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,414,919.25 1,127,852.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,127,852.75