Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 23-292-12-47 10-1G5104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-SJ-12-17.4/18.1 ACNH-P012(129) Progress payment No. 009 Payment period ending: 10-10-23 CALIFORNIA HIGHWAY CONSTRUCTION GROUP INC 1647 WILLOW PASS RD #150 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,015,604.29 186,058.48 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,015,604.29 186,058.48 5. Mobilization 158,978.10 0.00 6. Total Work Completed 2,174,582.39 7. Deductions -167,663.07 -127,663.07 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,006,919.32 58,395.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 58,395.41