Dept. of Trans. PROGRESS Serial No. Contract No. 21-172-09-04 10-1G7504 PROGRESS PAYMENT VOUCHER %complete: %time: 29% 28% Location: Federal Project: 10-MER-99-0.0 NONE Progress payment No. 006 Payment period ending: 06-20-21 BENTANCOURT BROS CONSTRUCTION INC 8015 WEST 11TH ST TRACY CA 95304 9303 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,467,250.50 479,761.00 2. a. Extra Work 3,289.85 0.00 b. Adustment Comp. 3. Materials on Hand 174,000.00 174,000.00 4. Earned Subject to Retention 1,644,540.35 653,761.00 5. Mobilization 684,000.00 144,000.00 6. Total Work Completed 2,154,540.35 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,318,540.35 787,761.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 787,761.00