Dept. of Trans. PROGRESS Serial No. Contract No. 19-142-10-58 10-1H3414 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 56% Location: Federal Project: 10-SJ-5-R21.4 B1IM-005-6(351) Progress payment No. 006 Payment period ending: 05-20-19 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 700,923.50 118,854.00 2. a. Extra Work 12,165.18 12,165.18 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 713,088.68 131,019.18 5. Mobilization 117,500.00 0.00 6. Total Work Completed 830,588.68 7. Deductions -1,992.50 52,942.50 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 828,596.18 183,961.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 183,961.68