Dept. of Trans. PROGRESS Serial No. Contract No. 21-116-14-39 10-1H3424 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 23% Location: Federal Project: 10-SJ-5-10.6 NONE Progress payment No. 002 Payment period ending: 04-20-21 AMERICAN CIVIL CONSTRUCTORS WEST COAST LLC 2990 BAY VISTA CT #D BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 319,523.61 237,900.94 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 319,523.61 237,900.94 5. Mobilization 172,500.00 172,500.00 6. Total Work Completed 492,023.61 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 492,023.61 410,400.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 410,400.94