Dept. of Trans. PROGRESS Serial No. Contract No. 18-330-09-43 10-1H4604 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 47% Location: Federal Project: 10-STA-132-0.0/13.3 ACNH-P132(53) Progress payment No. 003 Payment period ending: 11-20-18 CHESTER BROSS CONSTRUCTION CO PO BOX 430 HANNIBAL MO 63401 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 665,730.81 0.00 2. a. Extra Work 54,377.14 26,706.64 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 720,107.95 26,706.64 5. Mobilization 6. Total Work Completed 720,107.95 7. Deductions -32,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 688,107.95 24,706.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,706.64