Dept. of Trans. PROGRESS Serial No. Contract No. 25-262-16-18 10-1H5004 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 58% Location: Federal Project: 10-CAL-4-15.9/16.3 NONE Progress payment No. 007 Payment period ending: 09-20-25 VIKING CONSTRUCTION CO INC PO BOX 1508 RANCHO CORDOVA CA 95741-1508 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,436,162.00 195,332.00 2. a. Extra Work 88,485.88 88,485.88 b. Adustment Comp. 3. Materials on Hand 0.00 -32,965.00 4. Earned Subject to Retention 1,524,647.88 250,852.88 5. Mobilization 403,750.00 0.00 6. Total Work Completed 1,928,397.88 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,928,397.88 250,852.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 250,852.88