Dept. of Trans. PROGRESS Serial No. Contract No. 20-324-11-11 10-1H7804 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 64% Location: Federal Project: 10-SJ-0 NONE Progress payment No. 004 Payment period ending: 11-20-20 BURKE DIVERSIFIED 15115 TORREY PINES CIR CHOWCHILLA CA 93610 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 820,261.70 93,406.68 2. a. Extra Work 70,869.00 70,869.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 891,130.70 164,275.68 5. Mobilization 6. Total Work Completed 891,130.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 891,130.70 164,275.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 164,275.68