Dept. of Trans. PROGRESS Serial No. Contract No. 20-086-13-30 10-1H7904 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 71% Location: Federal Project: 10-SJ-0 NONE Progress payment No. 006 Payment period ending: 03-20-20 ANCHOR 41 CONSTRUCTION LLC 310 W MURRAY AVE VISALIA CA 93291 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 646,766.60 0.00 2. a. Extra Work 99,752.51 99,752.51 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 746,519.11 99,752.51 5. Mobilization 6. Total Work Completed 746,519.11 7. Deductions -25,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 721,519.11 109,752.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 109,752.51